13 | On Wednesday, September 23, 2026, at 11:50 am, Licensing Program Analyst (LPA) Giovanni Cristales conducted an unannounced inspection to conclude a complaint investigation and to deliver findings. LPA met with Director Alyse Sanders and advised the purpose of the inspection. Upon arrival, LPA toured the facility and observed 1 preschool classroom which is divided in half (Tigers & Bears), with 13 children and two (2) preschool teachers present. The facility is also licensed for the Infant program (364843655) and school age (364843657). The facility was found to be within ratio.
Community Care Licensing (CCL) received a complaint on 8/11/26. Throughout the course of the investigation, LPA conducted two inspections at the facility. The initial inspection visit was a joint visit. LPA’s collected the facility roster and made note of the room temperature (75 degrees). During the tour of the inspection, LPA’s observed the A.C. units to be in operable condition.